WE HAVE MOVED IN!!!

We began moving boxes on Thanksgiving morning, but our big thrust was on Friday, 11-23-2001.  We used four pickup trucks and made a bunch of trips between our storage unit (Read that as Parent's Garage) and the house, about 150 feet as the crow flies, 1/8 mile as the pickup drives.

Right now we have a sea of boxes and junk laid out in the garage and basement floor, all stacked one box deep.  It's complete chaos!  I can't find a thing.  After Mena spent two hours cleaning an extremely unpleasant looking refrigerator, we plugged it in and it began to make an awful squeaking noise.  I guess two years of storage was more than it could handle.

It was kind of pleasant yet frustrating, to find all sorts of stuff that I had looked for in our storage of stuff but could not find.  Now we have duplicated items of the inexpensive stuff.

First Night in the House

A major storm was brewing all Holiday weekend, and it hit about 2:45am Saturday morning.  We have no drapes or blinds on the windows.  As we went to sleep the first night, it was nice to look out upon all of the trees--so tranquil...  At 2:45am, I was awakened by the howling wind.  I looked out the window and noticed all those tall pine trees were now swaying violently in the wind.  Mind you, I've watched pine trees sway in the wind all my life, but never so close to my new home!  All I could focus on was the trees, and how much they seemed to be bending and swaying.  None broke, or fell over.  

 

Morning After Jitters

The next morning however, as I passed by and brushed a wall, the lights flickered.  My heart sank,  I thought, "No way, how could I have made an electrical wiring mistake?!"  So I bumped the wall, just to see, the lights appeared to flicker again! I bumped it again, nothing... I bumped it a 4th time, nothing, I thought that I must have fixed it.  As I was showering, and got the bathroom all steamed up, the lights again began to flicker.  I panicked, thinking again, "I must have screwed up the electrical".  A few hours later I was talking to my mother and she asked, "Are your lights flickering?"  My answer was, "Yes!  Yes they are, isn't that great!"  No longer was I worried that I screwed something up.

First snow of 2002

Latest Picture of Current Condition (02/02/2002)    -    More pictures here

Go to pictographic progression of the house

Task Status
Purchased Canned House Plans February 2000
Home Designer Modifications February - March 2000
Submit plans to contractors and wait for bids March - August 2000
House Plans Finalized October 2000
House Plans Submitted to Placer County for "Plan Check" November 7, 2000
Plans Approved by Placer County December 5, 2000
Rebid, revise, rework, find more money December 2000-February 2001
Sign Contract with General Contractor February 27, 2001
Finalize financing March 9, 2001
Sign papers at title company March 16, 2001
Break Ground March 21, 2001
Cut road, Brush Cleared March 28, 2001
Trench, bury conduit for Electricity, Cable, Telephone April 4, 2001
Dig Footings April 4, 2001
Build Foundation Forms April 5-18, 2001
Pour Foundation Footings April 19, 2001
Address Assigned - 720 Dogwood Bend April 25, 2001
Pour Garage and Basement Slabs April 27, 2001
Wood delivered to site April 30, May 1-3, 2001
Port-a-Potty emptied May 8, 2001
Wait for Framing Contractor to finish another job April 29, 2001 - May 15, 2001
Begin Framing - End Framing May 16, 2001 - June 23, 2001
Electrical (Rough) & low voltage (Hole Drilling) June 4, 2001 - August 10, 2001
Windows Installed June 14, 2001 - June 18, 2001
Roofing June 19, 2001 - July 11, 2001
Rough Electrical & low voltage (actually pulling wires) June 30, 2001 - August 10, 2001
Plumbing (Rough) July 2, 2001 - August 1, 2001
Heating & Air July 3, 2001 - August 1, 2001
Port-a-Potty emptied July 4, 2001
Port-a-Potty emptied July 11, 2001
Exterior Lathing  July 6, 2001 - July 31, 2001
Stucco August 31, 2001 - October 12, 2001
Trench, bury pipe and connect to MV water August 6, 2001 -
Install Septic System November 5, 2001 - November 10, 2001
Insulation August 14, 2001 - August 22, 2001
Drywall August 16, 2001 - August 27, 2001
Drywall Taping  August 28, 2001 - September 5, 2001
Texturing September 7, 2001
PG&E install electrical cable and Meter September 6, 2001 - September 7, 2001
Closet buildouts, window sills & baseboard installation September 10, 2001 - October 10, 2001
Cabinetry delivered September 20, 2001
Stair wood, treads and spindles delivered September 27, 2001
Interior Painting September 28, 2001 - October 15, 2001
Cabinets installed October 3-5
Brick hearth installed October 5
Richard tempts death, installs outside exterior lighting October 4-6
Tile work begins October 12, 2001
Concrete drive poured October 23, 2001
Heating & Cooling units installed October 24, 2001

 

Chronological progression of project  

Brush Cleared 1999 Site Prep March 2001 Building Forms April 14, 2001
October 1999

March 24-31 2001

April 14, 2001


Footings Poured: April 21, 2001 Slabs Poured: April 28, 2001 Slabs Poured: April 28, 2001

April 21, 2001

April 28, 2001

May 19, 2001


Footings Poured: April 21, 2001 Slabs Poured: April 28, 2001 Upper Floor Framing Begins..

May 21, 2001

May 23, 2001

June 2, 2001


Going up up up, 2001 Porch going in: June 6, 2001 Porch going in: June 6, 2001

June 4, 2001

June 6, 2001

June 9, 2001


Going up up up, 2001 Roof up Roof on, windows going in

June 15, 2001

June 20, 2001

June 22, 2001


Roofing begins Roof 95% complete! Roof 95% complete!

June 27, 2001

July 5, 2001

July 14, 2001


Stucco begins Stucco begins Stucco begins

August 31, 2001

September 7, 2001

September 16, 2001


Stucco begins Stucco begins Stucco begins

September 30 2001

October 7, 2001

October 14, 2001

Stucco begins Stucco begins First Snow!

October 28, 2001

October 28, 2001

February 3, 2002